Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 22nd Monthly EM&A Report Yau Lee Construction Co, Ltd 2023-09-13 |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
Document control |
||||||
Report
title |
22nd Monthly EM&A Report |
|||||
Document
ID |
MMR |
Project
number |
P520574 |
|||
File
path |
520574-0000-PLN-NM-00024 [0] |
|||||
Client |
|
|||||
Client
contact |
|
Client
reference |
|
|||
Rev |
Date |
Revision
details/status |
Author |
Reviewer |
Verifier
|
Approver |
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
1 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current
revision |
|
Approval |
|||
Reviewer’s signature |
|
Approver’s signature |
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
Title |
Associate, Environmental |
Title |
Environmental Team Leader |
All
rights reserved | The information/data furnished in our document is confidential
and competitive information proprietary to Aurecon or its subcontractors,
the release of which would harm the competitive position of Aurecon or its
sub-contractors/consultants. This information/data shall not be
reproduced, stored in a retrieval system, transmitted in any form or by
any means, used or disclosed in whole or in part, for any purpose other
than to evaluate and adjudicate this document. If Aurecon is shortlisted
or a contract is awarded to Aurecon as a result of this solicitation, or
in connection with the submission of such information/data, the right (and
the extent thereof) to reproduce, store, transmit, use or disclose this
information/data must, by agreement, be included in such contract.
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
Appendix 1 |
|
Appendix 2 |
|
Appendix 3 |
|
Appendix 4 |
|
Appendix 5 |
|
Appendix 6 |
|
Appendix 7 |
|
Appendix 8 |
|
Appendix 9 |
|
Appendix 10 |
|
Appendix 11 |
Notification of Environmental Quality Limits Exceedance |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 22nd Monthly EM&A Report presents the EM&A works conducted from 1 August 2023 to 31 August 2023 in accordance with the EM&A Manual.
Summary of Construction
Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
-
ELS works |
-
Pile
cap & tie beam construction |
-
Column
construction ( L1 to L2 ) |
-
Tower
Crane Erection |
-
Construction
of footing of tower crane |
Environmental Monitoring
and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
5 times |
-
Joint
Environmental Site Inspection |
5 times |
Nosie
5 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental Site
Inspection
Joint environmental site inspections were carried out on 04, 10, 17, 24 and 31 August 2023. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 4 and 31 August 2023. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
Future Key
Issues
Works to be undertaken in the next month include:
-
Pile cap & tie beam construction
works |
-
Superstructure construction (L1
to L2) |
-
Tower Crane Erection (TC2) |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
Construction Activities Undertaken |
-
Pile
cap & tie beam construction |
-
Column
construction ( L1 to L2 ) |
-
Tower
Crane Erection |
-
Construction
of footing of tower crane |
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
Notification of Construction Works as required
under Air Pollution Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
Registration of Waste Producer under Waste
Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
Construction Noise Permit |
GW-RS0453-23 |
4 December 2023 |
Approved
on 7 June 2023 |
Effluent Discharge License under Water Pollution
Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
Proposed Noise Monitoring Location |
Remark |
|
NM1 |
Ground Floor at Heng Fa Chuen
Block 50 |
- |
NM2b |
Pedestrian
road at Shing Tai Road |
* |
NM3 |
Rooftop of THEi Campus |
- |
Remark:
* - |
Hong Kong
Institute of Vocational Education (Chai Wan) - Academic Block (NM2) is the
noise monitoring stations for the construction phase EM&A programme as
identified in the approved EM&A Manual for the Project. The access to NM2
and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative noise
monitoring locations along Shing Tai Road and Sheung Mau Street was carried
out during the site visit on 4 October 2021. Lamp
Post no. 47447 at Sheung Mau Street (NM2a), which is located between project
site and original noise monitoring location, Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2), is found suitable and
available to be an alternative noise monitoring location for NM2. Also, NM2a,
which has a direct line of sight towards project site (where construction
works will be carried out and likely to have noise impacts), is located
closer to project site than NM2 and thus considered as a representative noise
monitoring location. Monitoring position at NM2a is proposed at 2m above
ground due to security concerns and minimize the road traffic noise
contribution. Noise measurement at NM2a will be considered as free-field and
a correction of +3dB(A) would be made to the noise monitoring results. The alternative location of NM2a, were
therefore proposed and agreed by the Independent Environmental Checker (IEC).
Due to
the adjustment of the location of NM2 to NM2a, the measured noise levels at NM2a
would represent the noise levels at NM2. To
respond to the comment raised by EPD on monitoring location of NM2a by email
dated 23 May 2022 and site meeting on 6 June 2022, the monitoring location of
NM2a was adjusted to the pedestrian road at Shing Tai Road (NM2b) which is located
between project site and original noise monitoring location, Hong Kong
Institute of Vocational Education (Chai Wan) - Academic Block (NM2). Compared
with NM2a, NM2b is far away from the traffic light and therefore should be
able to minimise the traffic noise issue. This arrangement was started from 28
June 2022 and has been agreed by the Independent Environmental Checker (IEC).
Noise measurement at NM2b will be considered as free-field and a correction
of +3dB(A) would be made to the noise monitoring results. Due to
the adjustment of the location of NM2a to NM2b, the measured noise level at
NM2b would represent the noise levels at NM2. |
Time Period |
Parameters |
Daytime on
normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5
mins) and L90(5 mins) |
Evening time
on all days (1900-2300 hrs) and Holidays (including Sundays) during daytime
and evening (0700-2300 hrs) |
Leq(5 mins), L10(5
mins) and L90(5 mins) |
All days
during the night-time (2300-0700 hrs of the next
day) |
Leq(5 mins) L10(5
mins) and L90(5 mins) |
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
NM1 |
Sound
Level Meter: Rion NL 52(s/n:01010406) Calibrator:
Larson Davis Cal 200(s/n: 11334) |
NM2b |
|
NM3 |
Monitoring Station |
Action Level |
Limit Level |
|
Noise Criteria, Leq(30mins),
dB(A) |
Remark |
||
NM1 |
When one
documented complaint is received |
75 |
Applicable during 0700 – 1900 hours, Monday to Saturday |
NM2b |
70 65 (during
examination) |
||
NM3 |
70 65 (during
examination) |
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
-
Use only well-maintained and regularly-serviced plant during the works;
-
Turn off or throttle down the plant in intermittent use to a minimum;
-
Orient the plant known to emit noise strongly in one direction to face
away from the NSRs;
-
Use silencers, mufflers and enclosures for plant where possible and
maintain properly throughout the works;
-
Site fixed plant as far away from NSRs as possible; and
-
Use stockpiles of excavated materials and other structures such as site
buildings effectively to screen noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield were adopted
as far as practicable following the Construction Noise Management Plan (CNMP).
• NM1: Railway noise, road traffic noise and Yau Lee Site.
• NM2b: Road traffic noise and Yau Lee Site.
• NM3: Cargo Handling Area and Yau Lee Site.
5.1.4
The methodology
is shown as below:
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30),
Construction noise level is calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise
level = Measured noise level
04 August 2023
• The waste skip was overloaded. The Contractor was reminded to schedule disposal of the non-inert waste when the waste skip is almost full.
• The stockpile of dusty material was placed near the channel at the site entrance. The Contractor was recommended to provide sandbag barriers surrounding the stockpile to prevent any washout into the channel.
• The Contractor was reminded to cover the cement bags entirely. Every stock of more than 20 bags of cement or dry pulverized fuel ash (PFA) shall be covered entirely by impervious sheeting or placed in an area sheltered on the top and 3 sides.
10 August 2023
• General waste was not properly disposed in enclosed bin. The Contractor was reminded to properly segregate and stored general waste in enclosed bins or compaction units separately from the construction and chemical wastes.
• The stagnant water was found in lower elevation in Zone C. The Contractor was reminded to divert the surface runoff to wastewater treatment facility.
• The chemical waste cupboard was not locked. The chemical waste cupboard should be locked.
17 August 2023
• Environmental Permit and Construction Noise Permit were not displayed at the relocated site entrance. The Contractor was reminded to display EP and CNP at the relocated site entrance.
• General refuse was found in the drip tray with chemical waste. General waste should be stored in enclosed bins or compaction units separately from the construction and chemical wastes. The Contractor was reminded to clear the drip tray and dispose of as chemical waste.
24 August 2023
• The chemical container was observed without drip tray and chemical label. The Contractor was reminded to provide drip tray for all chemical container and to display chemical label.
31 August 2023
• Stagnant water was found near the hoarding. The Contractor was reminded to clear the stagnant water.
- Lift
pit construction
- Pile
cap & tie beam construction
- Superstructure
construction (L1 to L2)
- Tower Crane Erection (TC2)
Monitoring Station |
EIA Predicted Construction Noise Levels,
dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
Leq(30mins),
Average |
Range |
||
NM1 |
62 |
65.1 |
63.3 |
62-64 |
NM2b |
69 |
73.4 |
70.3* |
67-72* |
NM3 |
66 |
69.8 |
67.0 |
65-68 |
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Appendix 11
There was no Notification of Environmental Quality Limits Exceedance
in the reporting month.
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999