Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 16th Monthly EM&A Report Yau Lee Construction Co, Ltd 2023-03-10 |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
Document control |
||||||
Report title |
16th Monthly EM&A Report |
|||||
Document ID |
MMR |
Project number |
P520574 |
|||
File path |
520574-0000-PLN-NM-00018 [0] |
|||||
Client |
|
|||||
Client contact |
|
Client reference |
|
|||
Rev |
Date |
Revision details/status |
Author |
Reviewer |
Verifier |
Approver |
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
1 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current revision |
|
Approval |
|||
Reviewer’s
signature |
|
Approver’s
signature |
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
Title |
Associate, Environmental |
Title |
Environmental Team Leader |
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data
shall not be reproduced, stored in a retrieval system, transmitted in any
form or by any means, used or disclosed in whole or in part, for any
purpose other than to evaluate and adjudicate this document. If Aurecon
is shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data shall
not be reproduced, stored in a retrieval system, transmitted in any form
or by any means, used or disclosed in whole or in part, for any purpose
other than to evaluate and adjudicate this document. If Aurecon is
shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix 1 |
|
Appendix 2 |
|
Appendix 3 |
|
Appendix 4 |
|
Appendix 5 |
|
Appendix 6 |
|
Appendix 7 |
|
Appendix 8 |
|
Appendix 9 |
|
Appendix 10 |
|
Appendix 11 |
Notification of Environmental Quality Limits Exceedance |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 16th Monthly EM&A Report presents the EM&A works conducted from 1 February 2023 to 28 February 2023 in accordance with the EM&A Manual.
Summary of
Construction Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
-
Piling tests |
-
Sheet piling work |
-
ELS works |
-
Pile cap & tie beam
construction |
-
Fabrication of precast elements |
Environmental
Monitoring and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
4 times |
-
Joint Environmental Site
Inspection |
4 times |
Nosie
4 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental Site
Inspection
Joint environmental site inspections were carried out on 03, 09, 16 and 23 February 2023. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 03 February 2023. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
Future Key Issues
Works to be undertaken in the next month include:
-
Sheet piling work |
-
ELS works |
-
Pile cap & tie beam construction
works |
-
Fabrication of precast elements |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
Construction Activities Undertaken |
-
Sheet piling work |
-
ELS works |
-
Pile cap & tie beam
construction |
-
Fabrication of precast elements |
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
Notification of Construction Works as required under Air Pollution
Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
Registration of Waste Producer under Waste Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
Construction Noise Permit |
GW-RS0672-22 |
13 April 2023 |
Approved on 16 August 2022 |
Effluent Discharge License under Water Pollution Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
Proposed Noise Monitoring Location |
Remark |
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
NM2b |
Pedestrian road at Shing Tai Road |
* |
NM3 |
Rooftop of THEi Campus |
- |
Remark: * - |
Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2) is the noise
monitoring stations for the construction phase EM&A programme as
identified in the approved EM&A Manual for the Project. The access to NM2
and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative noise
monitoring locations along Shing Tai Road and Sheung Mau Street was carried
out during the site visit on 4 October 2021. Lamp Post no. 47447 at Sheung
Mau Street (NM2a), which is located between project site and original noise
monitoring location, Hong Kong Institute of Vocational Education (Chai Wan) -
Academic Block (NM2), is found suitable and available to be an alternative
noise monitoring location for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m above ground due to security concerns and
minimize the road traffic noise contribution. Noise measurement at NM2a will
be considered as free-field and a correction of +3dB(A) would be made to the
noise monitoring results. The
alternative location of NM2a, were therefore proposed and agreed by the
Independent Environmental Checker (IEC). Due to the adjustment of the
location of NM2 to NM2a, the measured noise levels at NM2a would represent
the noise levels at NM2. To respond to the comment raised
by EPD on monitoring location of NM2a by email dated 23 May 2022 and site
meeting on 6 June 2022, the monitoring location of NM2a was adjusted to the
pedestrian road at Shing Tai Road (NM2b) which is located between project
site and original noise monitoring location, Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2). Compared with NM2a,
NM2b is far away from the traffic light and therefore should be able to
minimise the traffic noise issue. This arrangement was started from 28 June
2022 and has been agreed by the Independent Environmental Checker (IEC). Noise
measurement at NM2b will be considered as free-field and a correction of
+3dB(A) would be made to the noise monitoring results. Due to the adjustment of the
location of NM2a to NM2b, the measured noise level at NM2b would represent
the noise levels at NM2. |
Time Period |
Parameters |
Daytime on normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5 mins) |
Evening time on all days (1900-2300 hrs) and
Holidays (including Sundays) during daytime and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5 mins) |
All days during the night-time (2300-0700 hrs of the next day) |
Leq(5 mins) L10(5 mins) and L90(5 mins) |
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
NM1 |
Sound Level Meter: Rion NL
52(s/n:00131627) Calibrator: Larson Davis Cal
200(s/n: 11333) |
NM2b |
|
NM3 |
Monitoring Station |
Action Level |
Limit Level |
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
NM1 |
When one documented complaint is received |
75 |
Applicable
during 0700 – 1900 hours, Monday
to Saturday |
NM2b |
70 65
(during examination) |
||
NM3 |
70 65
(during examination) |
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
-
Use only well-maintained and regularly-serviced plant during the works;
-
Turn off or throttle down the plant in intermittent use to a minimum;
-
Orient the plant known to emit noise strongly in one direction to face
away from the NSRs;
-
Use silencers, mufflers and enclosures for plant where possible and
maintain properly throughout the works;
-
Site fixed plant as far away from NSRs as possible; and
-
Use stockpiles of excavated materials and other structures such as site
buildings effectively to screen noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield were adopted
as far as practicable following the Construction Noise Management Plan (CNMP).
• NM1: Railway noise, road traffic noise and Yau Lee Site.
• NM2b: Road traffic noise and Yau Lee Site.
• NM3: Cargo Handling Area and Yau Lee Site.
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30), Construction noise level is
calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise level = Measured noise level
03 February 2023
• The oil drums were observed without drip trays. Drip trays shall be provided to the oil drums.
• Movable
noise barrier was not provided to the sheet piling machine. The Contractor has
been reminded to provided noise barriers for the sheet piling machines as
required in the CNMP.
09 February 2023
• Part of the hoarding was removed on the site. At least 2.4m hoarding shall be provided.
• General waste and construction waste were not stored separately. General waste generated on-site shall be stored in enclosed bins or compaction units separately from the construction waste.
16 February 2023
• The work area was dry and fugitive dust was observed. The Contractor has been recommended to increase the frequency of waste disposal to prevent dust dispersion.
• The Contractor was reminded to fully cover the stockpile of dusty material using impervious sheets after construction work. The Contractor has reminded to fully cover the stockpile of dusty material after construction work.
23 February 2023
• Oil stains were observed near the GI machine. Oil stain shall be cleared and disposed of as chemical waste.
• The Contractor was reminded to ensure wastewater facility functioning properly. The wastewater treatment facility shall operate properly for the upcoming wet season.
• The Contractor was reminded to cover holes at the bottom of barriers to prevent leakage of run-off. The Contractor has been recommended to place sandbags at the bottom of the barriers to prevent any leakage outside the site boundary.
- Piling
tests
- Sheet
piling work
- ELS
works
- Pile
cap & tie beam construction
- Fabrication
of precast elements
Monitoring Station |
EIA Predicted Construction Noise Levels, dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
Leq(30mins),
Average |
Range |
||
NM1 |
62 |
65.1 |
64.7 |
62-67 |
NM2b |
69 |
73.4 |
71.7* |
69-73* |
NM3 |
66 |
69.8 |
68.3
|
68-69
|
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Appendix 11
There was no Notification of Environmental Quality Limits Exceedance
in the reporting month.
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999