Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 7th Monthly EM&A Report Yau Lee Construction Co, Ltd |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
Document control |
||||||
Report title |
Seventh Monthly EM&A Report |
|||||
Document ID |
MMR |
Project number |
P520574 |
|||
File path |
520574-0000-PLN-NM-0008 [0] |
|||||
Client |
|
|||||
Client contact |
|
Client reference |
|
|||
Rev |
Date |
Revision details/status |
Author |
Reviewer |
Verifier |
Approver |
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
1 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current revision |
|
Approval |
|||
Reviewer’s
signature |
|
Approver’s
signature |
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
Title |
Principal Consultant, Environmental |
Title |
Environmental Team Leader |
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
Construction Programme |
|
Project Organization Chart and Contact Details |
|
Monitoring Programme for Reporting Period |
|
Calibration Certificates |
|
Event and Action Plan |
|
Implementation Status of Mitigation Measures |
|
Monitoring Results with Graphical Presentations |
|
Waste Flow Table |
|
Joint site inspection record for Reporting Period |
|
Monitoring Schedule for the Next Month |
|
Appendix 11 |
Notification of Environmental Quality Limits Exceedance |
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position of
Aurecon or its sub-contractors/consultants. This information/data shall not
be reproduced, stored in a retrieval system, transmitted in any form or by
any means, used or disclosed in whole or in part, for any purpose other
than to evaluate and adjudicate this document. If Aurecon is shortlisted or
a contract is awarded to Aurecon as a result of this solicitation, or in
connection with the submission of such information/data, the right (and the
extent thereof) to reproduce, store, transmit, use or disclose this
information/data must, by agreement, be included in such contract.
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 7th Monthly EM&A Report presents the EM&A works conducted from 1 May 2022 to 31 May 2022 in accordance with the EM&A Manual.
Summary of
Construction Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
-
Pre-drilling work. (Zone A
& Zone B) |
-
Piling work |
-
Tree protection works |
Environmental
Monitoring and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
5 times |
-
Joint Environmental Site
Inspection |
4 times |
Nosie
5 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Chai Wan THEi Campus has been re-opened for access. Therefore, the adjusted monitoring location at NM3a has been resumed back to NM3 (Rooftop of Chai Wan THEi Campus) starting from 10 May 2022.
During reporting period, school examinations were carried out from 14 May to 27 May 2022 (except 24 May 2022) at Chai Wan THEi Campus. Limit level of 65 dB(A) is applied for NM3 during the exam period.
Environmental Site
Inspection
Joint environmental site inspections were carried out on 06, 12, 19 and 26 May 2022. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 6 May 2022. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
Future Key Issues
Works to be undertaken in the next month include:
-
Tree protection works |
-
Piling works |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
Construction Activities Undertaken |
-
Pre-drilling work. (Zone A
& Zone B) |
-
Pilling work |
-
Tree protection works |
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
Notification of Construction Works as required under Air Pollution Control
(Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
Registration of Waste Producer under Waste Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
Construction Noise Permit |
GW-RS0245-22 |
13 October 2022 |
Approved on 14 April 2022 |
Effluent Discharge License under Water Pollution Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
Proposed Noise Monitoring Location |
Remark |
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
NM2a |
Lamp Post no. 47447 at Sheung Mau Street |
* |
NM3 |
Rooftop of THEi Campus |
* |
Remark: * - |
Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2) is the noise
monitoring stations for the construction phase EM&A programme as
identified in the approved EM&A Manual for the Project. The access to NM2
and Knight Court (as a VTC Senior Quarters and NSR3 in approved EIA) were
denied. A search for alternative noise
monitoring locations along Shing Tai Road and Sheung Mau Street was carried
out during the site visit on 4 October 2021. Lamp Post no. 47447 at Sheung
Mau Street (NM2a), which is located between project site and original noise
monitoring location, Hong Kong Institute of Vocational Education (Chai Wan) -
Academic Block (NM2), is found suitable and available to be an alternative
noise monitoring location for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m above ground due to security concerns and
minimize the road traffic noise contribution. Noise measurement at NM2a will
be considered as free-field and a correction of +3dB(A) would be made to the
noise monitoring results. The
alternative location of NM2a, were therefore proposed and agreed by the
Independent Environmental Checker (IEC). Due to the adjustment of the
location of NM2 to NM2a, the measured noise levels at NM2a would represent
the noise levels at NM2. THEi (Chai Wan Campus) has been
re-opened for access. Therefore, the adjusted monitoring location at NM3a has
been resumed back to NM3 (Rooftop of Chai Wan THEi
Campus) starting from 10 May 2022. |
NM3a
Time Period |
Parameters |
Daytime on normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5 mins) |
Evening time on all days (1900-2300 hrs) and
Holidays (including Sundays) during daytime and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5 mins) |
All days during the night-time (2300-0700 hrs of the next day) |
Leq(5 mins) L10(5 mins) and L90(5 mins) |
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
NM1 |
Sound Level Meter: Rion NL
52(s/n:00643040) and (s/n:01010406) Calibrator: Larson Davis Cal
200(s/n: 16878) |
NM2a |
|
NM3/ NM3a |
Monitoring Station |
Action Level |
Limit Level |
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
NM1 |
When one documented complaint is received |
75 |
Applicable
during 0700 – 1900 hours, Monday
to Saturday |
NM2a |
70 65
(during examination) |
||
NM3/ NM3a |
70 65
(during examination) |
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
-
Use only well-maintained and regularly-serviced plant during the works;
-
Turn off or throttle down the plant in intermittent use to a minimum;
-
Orient the plant known to emit noise strongly in one direction to face
away from the NSRs;
-
Use silencers, mufflers and enclosures for plant where possible and
maintain properly throughout the works;
-
Site fixed plant as far away from NSRs as possible; and
-
Use stockpiles of excavated materials and other structures such as site
buildings effectively to screen noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield will be adopted
when hoarding work is conducted.
• NM1: Road traffic noise and railway noise.
• NM2a: Road traffic noise and Yau Lee Site.
• NM3/ NM3a: Road traffic noise, Cargo Handling Area and Yau Lee Site.
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30), Construction noise level is
calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise level = Measured noise level
In the reporting period, baseline
corrections were made on 3, 10, 17, 24 and 31 May 2022 at NM2a, and on 10, 24 May 2022 at NM3.
06 May 2022
• No particular findings
12 May 2022
• No particular findings
19 May 2022
• Oil stain was observed near the GI Machine. Oil stain shall be cleared and disposed of as chemical waste.
• A vehicle wasn’t cleaned thoroughly before leaving the site. The Contractor was recommended to enhance wheel washing system for vehicles before they leave the site.
26 May 2022
• The waste storage tank was almost fully loaded. The Contractor was recommended to increase the frequency of waste disposal if necessary to avoid waste accumulation.
- Tree protection works
- Piling works
Monitoring Station |
EIA Predicted Construction Noise Levels, dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
Leq(30mins),
Average |
Range |
||
NM1 |
62 |
65.1 |
65.8 |
65-68 |
NM2a |
69 |
73.4 |
74.6(68*) |
74-75(65-70*) |
NM3 |
66 |
69.8 |
69.2(66.2*) |
68-72(59-68*) |
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Appendix 11
There was no Notification of Environmental Quality Limits Exceedance
in the reporting month.
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999