Contract
No. SS H504 Design and Construction of Chai Wan Government Complex and
Vehicle Depot 13th Monthly EM&A Report Yau Lee Construction Co, Ltd |
Document control record
Document prepared by:
Unit 1608, 16/F, Tower B, Manulife Financial Centre,
223 – 231 Wai Yip Street, Kwun Tong, Kowloon
Hong Kong S. A. R.
T |
+852 3664 6888 |
A person using
a) Using the documents or data in electronic
form without requesting and checking them for accuracy against the original
hard copy version.
b)
Using
the documents or data for any purpose not agreed to in writing by
Document control |
||||||
Report title |
13th Monthly EM&A Report |
|||||
Document ID |
MMR |
Project number |
P520574 |
|||
File path |
520574-0000-PLN-NM-00014 [0] |
|||||
Client |
|
|||||
Client contact |
|
Client reference |
|
|||
Rev |
Date |
Revision details/status |
Author |
Reviewer |
Verifier |
Approver |
0 |
|
Submitted to IEC |
Various |
K.Chau |
|
FL |
1 |
12 December 2022 |
Submitted to IEC |
Various |
K.Chau |
|
FL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Current revision |
|
Approval |
|||
Reviewer’s
signature |
|
Approver’s
signature |
|
Name |
Keith Chau |
Name |
Fredrick
Leong |
Title |
Associate, Environmental |
Title |
Environmental Team Leader |
All
rights reserved | The information/data furnished in our document is
confidential and competitive information proprietary to Aurecon or its
subcontractors, the release of which would harm the competitive position
of Aurecon or its sub-contractors/consultants. This information/data shall
not be reproduced, stored in a retrieval system, transmitted in any form
or by any means, used or disclosed in whole or in part, for any purpose
other than to evaluate and adjudicate this document. If Aurecon is
shortlisted or a contract is awarded to Aurecon as a result of this
solicitation, or in connection with the submission of such
information/data, the right (and the extent thereof) to reproduce, store,
transmit, use or disclose this information/data must, by agreement, be
included in such contract.
Contents
3 Environmental Monitoring Requirements
4 Implementation Status on Environmental Mitigation
Measures
6 Environmental Site Inspection
7 Environmental Non-conformance
9 Review of EM&A Data and EIA Predictions
Appendix
Appendix 1 |
|
Appendix 2 |
|
Appendix 3 |
|
Appendix 4 |
|
Appendix 5 |
|
Appendix 6 |
|
Appendix 7 |
|
Appendix 8 |
|
Appendix 9 |
|
Appendix 10 |
|
Appendix 11 |
Notification of Environmental Quality Limits Exceedance |
Aurecon Hong Kong Limited (Aurecon) was commissioned by the Yau Lee Construction Co, Ltd (Yau Lee) to undertake the role of Environmental Team (ET) for carrying out the environmental monitoring and audit (EM&A) works for the “Contract No. SS H504 Design and Construction of Chai Wan Government Complex and Vehicle Depot (The Project).
An Environmental Permit (EP) No. EP-505/2015 was issued by the Environmental Protection Department (EPD) on 17 December 2015 for the construction of this project based on the Environmental Impact Assessment (EIA) Report (Register No: AEIAR-191/2015) approved by the EPD. The latest EP No. EP-505/2015/A was subsequently issued by the EPD on 8 November 2019 based on the documents (including an Environmental Review Report (ERR)) for the application of Variation of Environmental Permit.
The construction phase and EM&A programme of the Project commenced on 25 November 2021.
This 13th Monthly EM&A Report presents the EM&A works conducted from 1 November 2022 to 30 November 2022 in accordance with the EM&A Manual.
Summary of
Construction Works undertaken during Report Period
The major construction works undertaken during the reporting period include:
-
Pre-drilling works (Zone A
& Zone B) |
-
Pilling works |
-
Tree protection works |
-
Pre-boarding work for sheet
pile installation |
Environmental
Monitoring and Audit Progress
A summary of the monitoring activities in this reporting period is listed below:
-
Construction Noise Monitoring
during normal weekdays at each monitoring station |
5 times |
-
Joint Environmental Site
Inspection |
4 times |
Nosie
5 sets of 30-minute construction noise measurement were carried out at each monitoring stations during normal weekdays of the reporting period. No exceedance of Action and Limit Levels of construction noise was recorded during the reporting period.
Environmental Site
Inspection
Joint environmental site inspections were carried out on 04, 09, 17 and 24 November 2022. The joint environmental site inspection was carried out by the representatives of the Engineer's Representative (ER), the Contractor, IEC and the ET on 04 November 2022. The Contractor has generally implemented the mitigation measures as recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance of the Action and Limit Levels of construction noise was recorded at designated monitoring stations during the reporting period.
No non-compliance event was recorded during the reporting period.
No environmental complaint and summons/prosecutions was received in this reporting period.
Future Key Issues
Works to be undertaken in the next month include:
-
Pilling work |
-
Tree protection works |
-
Sheet pile installation |
-
ELS works |
-
Off-site mock up construction |
Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoff and waste management.
Project site
Construction Activities Undertaken |
-
Pilling work |
-
Tree protection works |
-
Piling work |
Permit / Licenses / Notification |
Reference |
Validity Period |
Remark |
Environmental Permit (EP) |
EP-505/2015/A |
Throughout the Contract |
Permit granted on 8 November 2019 |
Notification of Construction Works as required under Air Pollution
Control (Construction Dust) Regulation |
469716 |
Throughout the Contract |
Approved on 21 July 2021 |
Registration of Waste Producer under Waste Disposal Ordinance |
7041313 |
Throughout the Contract |
Approved on 13 August 2021 |
Registration as Chemical Waste Producer |
5213-163-Y2782-01 |
Throughout the Contract |
Approved on 24 August 2021 |
Construction Noise Permit |
GW-RS0672-22 |
13 April 2023 |
Approved on 16 August 2022 |
Effluent Discharge License under Water Pollution Control Ordinance |
WT00038924-2021 |
30 September 2026 |
Approved on 9 December 2021 |
Proposed Noise Monitoring Location |
Remark |
|
NM1 |
Ground Floor at Heng Fa Chuen Block 50 |
- |
NM2b |
Pedestrian road at Shing Tai Road |
* |
NM3 |
Rooftop of THEi Campus |
- |
Remark: * - |
Hong Kong Institute of Vocational
Education (Chai Wan) - Academic Block (NM2) is the noise monitoring stations
for the construction phase EM&A programme as identified in the approved
EM&A Manual for the Project. The access to NM2 and Knight Court (as a VTC
Senior Quarters and NSR3 in approved EIA) were denied. A search for alternative noise monitoring
locations along Shing Tai Road and Sheung Mau Street was carried out during
the site visit on 4 October 2021. Lamp Post no. 47447 at Sheung
Mau Street (NM2a), which is located between project site and original noise
monitoring location, Hong Kong Institute of Vocational Education (Chai Wan) -
Academic Block (NM2), is found suitable and available to be an alternative
noise monitoring location for NM2. Also, NM2a, which has a direct line of
sight towards project site (where construction works will be carried out and
likely to have noise impacts), is located closer to project site than NM2 and
thus considered as a representative noise monitoring location. Monitoring
position at NM2a is proposed at 2m above ground due to security concerns and
minimize the road traffic noise contribution. Noise measurement at NM2a will
be considered as free-field and a correction of +3dB(A) would be made to the
noise monitoring results. The
alternative location of NM2a, were therefore proposed and agreed by the
Independent Environmental Checker (IEC). Due to the adjustment of the
location of NM2 to NM2a, the measured noise levels at NM2a would represent
the noise levels at NM2. To respond to the comment raised
by EPD on monitoring location of NM2a by email dated 23 May 2022 and site
meeting on 6 June 2022, the monitoring location of NM2a was adjusted to the
pedestrian road at Shing Tai Road (NM2b) which is located between project
site and original noise monitoring location, Hong Kong Institute of
Vocational Education (Chai Wan) - Academic Block (NM2). Compared with NM2a,
NM2b is far away from the traffic light and therefore should be able to
minimise the traffic noise issue. This arrangement was started from 28 June
2022 and has been agreed by the Independent Environmental Checker (IEC). Noise
measurement at NM2b will be considered as free-field and a correction of
+3dB(A) would be made to the noise monitoring results. Due to the adjustment of the
location of NM2a to NM2b, the measured noise level at NM2b would represent
the noise levels at NM2. |
Time Period |
Parameters |
Daytime on normal weekdays (0700-1900 hrs) |
Leq(30 mins), L10(5 mins) and L90(5 mins) |
Evening time on all days (1900-2300 hrs) and Holidays
(including Sundays) during daytime and evening (0700-2300 hrs) |
Leq(5 mins), L10(5 mins) and L90(5 mins) |
All days during the night-time (2300-0700 hrs of the next day) |
Leq(5 mins) L10(5 mins) and L90(5 mins) |
Monitoring Station |
Monitoring Equipment (Sound Level Meter and Calibrator) |
NM1 |
Sound Level Meter: Rion NL
52(s/n:00131627) Calibrator: Larson Davis Cal
200(s/n: 11333) |
NM2b |
|
NM3 |
Monitoring Station |
Action Level |
Limit Level |
|
Noise Criteria, Leq(30mins), dB(A) |
Remark |
||
NM1 |
When one documented complaint is received |
75 |
Applicable
during 0700 – 1900 hours, Monday
to Saturday |
NM2b |
70 65
(during examination) |
||
NM3 |
70 65
(during examination) |
I.
The timing and sequence of construction activities were carefully
arranged.
II.
QPME were used to reduce the excessive noise impact.
III.
Good site practices were implemented to reduce noise impact of the site
activities. The practices are listed as below:
-
Use only well-maintained and regularly-serviced plant during the works;
-
Turn off or throttle down the plant in intermittent use to a minimum;
-
Orient the plant known to emit noise strongly in one direction to face
away from the NSRs;
-
Use silencers, mufflers and enclosures for plant where possible and
maintain properly throughout the works;
-
Site fixed plant as far away from NSRs as possible; and
-
Use stockpiles of excavated materials and other structures such as site
buildings effectively to screen noise from the works.
IV.
Movable noise barrier/acoustic sheet barriers as noise shield were adopted
as far as practicable following the Construction Noise Management Plan (CNMP).
• NM1: Railway noise, Yau Lee Site and Road traffic noise.
• NM2b: Road traffic noise and Yau Lee Site.
• NM3: Cargo Handling Area and Yau Lee Site.
·
When Measured noise level (Leq
30mins) > Baseline noise level (Leq30), Construction noise level is
calculated
·
Construction noise level = Measured noise level (Leq 30 mins) – Baseline noise level
·
If Measured noise level (Leq
30mins) < Baseline noise level, Corrected noise level = Measured noise level
04 November 2022
• A mobile crane was observed without NRMM label. A valid
NRMM label shall be provided for the mobile crane.
09 November 2022
• No particular findings.
17 November 2022
• An oil drum was observed without chemical label and drip tray was not used properly. The Contractor has been reminded to provide chemical label for oil drum. Drip tray shall be used to store oil drum.
24 November 2022
• NRMM label was observed inaccurate. The Contractor has been reminded to replace the NRMM label.
- Tree protection works
- Piling works
- Pre-drilling works (Zone A & Zone B)
- Hoarding erection
- Sheet pile installation
- ELS works
- Off-site mock up construction
Monitoring Station |
EIA Predicted Construction Noise Levels, dB(A) |
Baseline Noise Levels, dB(A) |
Noise Monitoring Results, dB(A) |
|
|
Leq(30mins),
Average |
Range |
||
NM1 |
62 |
65.1 |
63.3 |
60-66 |
NM2b |
69 |
73.4 |
71.2* |
67-73* |
NM3 |
66 |
69.8 |
68.0(66.4#)
|
67-70
(58-68#) |
#Baseline corrections were carried out as the measured noise
levels exceeded the limit noise levels and they were higher than the baseline
levels for NM3. The corrected noise levels which solely represent the noise
levels of Construction works are lower than the noise criteria. As such the EAP
was not triggered. Details are mentioned in Section 5.1.3 and summarised in
Appendix 7.
Appendix 1
Appendix 2
Appendix 3
Appendix 4
Appendix 5
Appendix 6
Appendix 7
Appendix 8
Appendix 9
Appendix 10
Appendix 11
There was no Notification of Environmental Quality Limits Exceedance
in the reporting month.
Prepared by:
Aurecon Hong Kong
Limited
Unit 1608, 16/F, Tower
B, Manulife Financial Centre,
223 – 231 Wai Yip
Street, Kwun Tong,
Kowloon Hong Kong S.
A. R.
T: +852 3664 6888
F: +852 3664 6999